Comparing Project Versions

Notes:

To compare a project versionClosed A read-only data capture of the project in a particular moment in time. or baselineClosed A static data capture of the original or re-planned project against which changes are compared. with another project version:

  1. On a project record, click Actions | Project Versioning | Compare Versions. Using Classic:Closed On the Managed Versions related list, click Compare Version. The Compare Versions page opens.
  2. Select project versions from the Compare and To drop-down lists.
  3. Click Compare.
    The following are displayed on the Compare Versions page:

Viewing the Standard Comparison Overview

Standard Headline Overview Standard Headline Overview Data Notes
Assignments
  • Number of Assignments
  • Scheduled Hours
 
Budgets
  • Budget Total
  • Approved
 
Estimates Vs Actuals
  • Estimated Hours
  • Actual Hours
Version records contain summaries of total hours listed. If you use multiple time periods for Estimates vs Actuals, such as quarter, month, and week, your hours are summarized together.
Issues
  • Number of Issues
  • Average Severity
  • Maximum Severity
All issues irrespective of status. The average severity value is the mean of all issue severities in the project version.
The maximum severity value is the issue with the highest severity in the project version.
Milestones
  • Number of Milestones
 
Phases
  • Number of Phases
 
Project Tasks
  • Number of Project Tasks
  • Estimated Hours
  • Completed Project Tasks
The project tasks value excludes parent tasks.
Resource Requests
  • Number of Resource Requests
  • Requested Hours
All resource requests irrespective of status.
Risks
  • Number of Risks
  • Average Severity
  • Maximum Severity
All risks irrespective of status. The average severity value is the mean of all risk severities in the project version.
The maximum severity value is the risk with the highest severity in the project version.