Task Grid Fields
These fields are set in the Project Task object.
From Setup:
- In section Platform Tools, select Objects and Fields | Object Manager | Project Task.
- Click Fields & Relationships.
This table details the fields in the Fields & Relationships list.
Field Label |
Field Name |
Description |
Data Type |
---|---|---|---|
WBS Element Number | WBS_Element_Number |
A work breakdown structure (WBS) that is generated automatically from an existing project hierarchy, and updated automatically as the hierarchy changes. |
Text(100) |
Project Task Name | Name | The name that a user enters. |
Text(80) |
Start Date | Start_Date |
The start date of the project or project task. The format is dependent on the computer's location. |
Formula (Date) |
End Date | End_Date |
The end date of the project or project task. The format is dependent on the computer's location. |
Formula (Date) |
Duration Units | Duration_Unit |
Specifies the units of time used for project tasks. Valid values are hours or days. The default value is days. |
Text(10) |
Estimated Hours | Estimated_Hours | The estimated hours that the user enters for the task. Values are rolled up to the estimated hours for the parent task and the project. | Number (16,2) |
Actual Hours | Actual Hours |
A read-only field for the hours saved, submitted or approved on timecards for a task. Hours for child tasks are rolled up to their parent task, and the total hours are rolled up to the project. |
Number (16,2) |
Timecard Actual Hours |
Timecard Actual Hours | A read-only field for the time completed against a timecard for a project task, where the timecard status matches any of those defined in the Timecard Statuses field in the Task Management Settings custom setting. | Number (16,2) |
Assigned Resources | Assigned_Resources | A comma-separated list of the details of resources or roles assigned to project tasks. | Text(255) |
Work Calendar | Work_Calendar | The work calendar used to schedule a project task in Gantt. |
Lookup(Work Calendar) |