Gantt Fields

This topic describes the fields in the Gantt task grid for administrators.

Task Grid Fields

These fields are set in the Project Task object.

From Setup:

  1. In section Platform Tools, select Objects and Fields | Object Manager | Project Task. Using ClassicClosed In section App Setup, click Create | Objects | Project Task.
  2. Click Fields & Relationships.

This table details the fields in the Fields & Relationships list.

Field Label

Field Name

Description

Data Type

WBS Element Number WBS_Element_Number

A work breakdown structure (WBS) that is generated automatically from an existing project hierarchy, and updated automatically as the hierarchy changes.

Text(100)
Project Task Name Name The name that a user enters.
Text(80)
Start Date Start_Date

The start date of the project or project task.

The format is dependent on the computer's location.

Formula (Date)
End Date End_Date

The end date of the project or project task.

The format is dependent on the computer's location.

Formula (Date)
Duration Units Duration_Unit

Specifies the units of time used for project tasks. Valid values are hours or days. The default value is days.

Text(10)
Estimated Hours Estimated_Hours The estimated hours that the user enters for the task. Values are rolled up to the estimated hours for the parent task and the project. Number (16,2)
Actual Hours Actual Hours

A read-only field for the hours saved, submitted or approved on timecards for a task.

Hours for child tasks are rolled up to their parent task, and the total hours are rolled up to the project.

Number (16,2)

Timecard Actual Hours

Timecard Actual Hours A read-only field for the time completed against a timecard for a project task, where the timecard status matches any of those defined in the Timecard Statuses field in the Task Management Settings custom setting. Number (16,2)
Assigned Resources Assigned_Resources A comma-separated list of the details of resources or roles assigned to project tasks. Text(255)
Work Calendar Work_Calendar The work calendar used to schedule a project task in Gantt.