Project Task Gantt Custom Preferences

You can change a preference in the Project Task Gantt Custom Preferences page. When you change a preference, an equivalent mapped custom setting is also updated in Project Task Gantt Settings and Preferences

Updates to custom preferences apply immediately when changed in Project Task Gantt and do not require a refresh, except for:

  • Zoom level in the Display tab.
  • Task selection in the Tasks tab.

The Zoom level and Task selection custom preference settings apply to the initial load of Project Task Gantt. Your selected behavior displays in subsequent loading of Project Task Gantt.

To modify custom preferences:

  1. In the Toolbar of Project Task Gantt click Preferences Panel.
  2. Select a Custom Preferences tab:
  1. Click Back to Project Task Gantt when finished.