Calculating Future Scheduled Hours
To calculate Future Scheduled Hours for assignments:
For an individual schedule:
- On the Schedule Detail page, check Action: Update Future Scheduled Hours.
- Click Save.
Updated hours display in Future Scheduled Hours on the Schedule Detail page.
To calculating future scheduled hours immediately:
- On the PSA Administration page, click PSA Batch Processes | Calculate Future Time on Schedules. Calculate Future Time on Schedules window opens.
- Click Run. The batch job is submitted and the Future Scheduled Hours are calculated.
To schedule a batch job to calculate future scheduled hours:
- On the PSA Administration page, click PSA Batch Processes | Calculate Future Time on Schedules. Calculate Future Time on Schedules window opens.
- Click Schedule.
- Set the schedule day, time, and frequency.
- [Optional] To change your selection, click Back.
- Click Schedule.
Using Classic or Visualforce pages
For submitting a batch of Future Scheduled Hours:
- Click the PSA Administration tab.
- In the Calculate Future Time on Schedules option, click Submit Batch to immediately calculate all Future Scheduled Hours.
For scheduling a batch of Future Scheduled Hours to run at a specific date and time:
- Click the PSA Administration tab.
- In the Schedule option, specify the interval to schedule and the time of day to start the batch job.
- In the Calculate Future Time on Schedules option, click Schedule Batch to schedule the batch calculation of Future Scheduled Hours.