If you suspect that some actuals are incorrect, you can verify them using the Actuals Verifier. If the Actuals Verifier finds discrepancies, there are several actions that you can take including:
If PSA is configured to calculate actuals in scheduled mode, process any unprocessed transaction deltas.
To process unprocessed transaction deltas:
Click the Actuals Verifier tab.
If there are unprocessed transaction deltas, click Process to process them.
To verify actuals:
Click the Actuals Verifier tab.
Click Lock Actuals.
Select the scope to carry out the verification on:
Select Region, Practice, Group, Project or Resource. If verifying actuals for a project or a resource and you want to verify actuals for all projects or resources, Select the Include all Projects or Resources checkbox.
Select the time period, or if you want to include all time periods between the start and end dates of the selected objects, select the checkbox.
Click Check Verification Scope.
Ensure the message at the top of the page indicates that the selected scope is within the 10,000 record limit. If this is not the case, change the selected scope and check the verification scope again.
Click Start Verification.
The Verification Results appear after a few moments.
If no differences are found, or if discrepancies were found but you want to resolve them at a later date:
Click Start Over to remove verification actuals.
The verification options re-appear after a few moments.
Click Unlock Actuals.
If PSA is configured to calculate actuals in scheduled mode, re-schedule the batch jobs that you unscheduled earlier.
Notify users that PSA is available again.
If the Actuals Verifier found differences between the transactions and the actuals records, click the link to review them. Differences are highlighted like this.
Click the image to expand it.
Deleting Actuals
If you verified actuals, the actuals verifier found discrepancies and you now want to delete all actuals and re-calculate them:
If you previously verified actuals but removed the verification actuals after doing so, verify actuals again on the objects and time periods on which you suspect there to be inconsistencies.
Copy all new actuals values to their parent Region/Practice/Group/Project/Resource. Do one of the following:
Use the Data Loader to select the Action: Update Current Time Period checkboxes and clear the Time Period fields on the region, practice, group, project or resource.
Schedule the RPGPRMaintenanceSchedule Apex class with start and end dates in the near future.
If PSA is configured to calculate actuals in scheduled mode, re-schedule the batch jobs that you unscheduled earlier.