Start Date |
Filters the resource requests based on the start date. |
Search drop-down list and field |
Filters the resource requests and resources based on criteria you specify. You can use the Advanced option to search in specific fields. |
Schedule Pattern |
Allows you to change the schedule pattern for the . You can select one of the following options: - Select Calculate End Date, Level Schedule: Calculates the end date taking into account holidays and other assignments that the has.
- Select Calculate End Date, Ignore Availablity: Calculates the End Date ignoring any holidays or other assignments that the resource has.
- Adjust Hours Per Day: Calculates the hours per day based on the project end date and the Scheduled Hours. The Scheduled Hours are distributed evenly between the start and end dates.
- Custom: Calculates the end date based on hours you enter in the Day fields. For instance, if you want the resource to work on the for four days a week you can enter hours in the day fields to calculate the end date based on a four day week. After selecting this option, a popup window appears where you can enter this information.
|