Scheduling Strategies Overview
You set the scheduling strategy when you create a new assignmentConnection between a resource and a project. using the Assign Resource section on the Resource Request page, and also by using the Assign Resource button or Assign Multiple Resources button on the Project Assignment related list.
When assigning a resource to a project using the Assign Resource button on the Project Assignment related list, you can also select a scheduling strategy before you click Update Schedule for the first time. After creating an assignment, you can edit the schedule associated with it.
Some scheduling strategies and options may not be available when using the Assign Multiple Resources button on the Project Assignment related list.
You can use the following available scheduling strategies depending on the options your administrator has set.
Key:
- N = Strategy not supported in the Schedule Strategy field of the Reschedule section when you click Edit Schedule on the Assignment page to update an assignment schedule.
- L = Strategy not supported for resource requests in Lightning experience.
Scheduling Strategy |
Key |
Description | Usage |
---|---|---|---|
Adjust Hours Per Day | L | Calculates the hours per day based on the project end date and the Scheduled Hours. | Scheduled Hours are distributed evenly between the start and end dates for the resource's working days based on the resource's work calendarA calendar that defines the working days, hours and public holidays for a resource, region, practice or group.. Consequently, the hours per day might not match the resource's work calendar. If the Adjust Hours Strategy Respects Holidays custom setting in the Assignment settings is set, the schedule respects holidays and schedule exceptions are created for them. Hours are spread across other days. For more information, see Schedule Exceptions Overview. |
Calculate End Date, Ignore Availability | Calculates the end date ignoring the resourceA contact that works on a project. 's other assignments. | A resource's work calendar is set to 8 hours per working day:
|
|
Calculate End Date, Level Schedule |
Calculates the end date for the assignment respecting the resource’s other assignments and holidays on their work calendar. The end date on the Schedule Details is calculated automatically. |
A resource's work calendar is set to 8 hours per working day:
|
|
Custom | N | Calculates the end date based on hours you enter in the Day fields. | For a resource working on an assignment for four days a week, enter hours in the Day fields for four days only. The end date is based on the four days, respecting public holidays, but excluding weekends. |
Percent Allocation | L | Calculates the hours per day based on the percentage allocation in the Date Range lines. | You can add several date range lines and specify a different percentage allocation on each date range. When you create an assignment or update the scheduling strategy on an assignment using this strategy schedule exceptions are created based on the date ranges and percent allocation that you enter. For more information, see Schedule Exceptions Overview. |
Zero Hour Schedule | N | Allows you to create assignments with zero hours for each day. | You can create resource requests with zero hours and then staff, assign or hold the resource requests. |