Calculating Future Scheduled Hours
To calculate Future Scheduled Hours for assignments:
For an individual schedule:
- On the Schedule Detail page, check Action: Update Future Scheduled Hours.
- Click Save.
Updated hours display in Future Scheduled Hours on the Schedule Detail page.
For submitting a batch of Future Scheduled Hours:
- Click the PSA Administration tab.
- In the Calculate Future Time on Schedules option, click Submit Batch to immediately calculate all Future Scheduled Hours.
For scheduling a batch of Future Scheduled Hours to run at a specific date and time:
- Click the PSA Administration tab.
- In the Schedule option, specify the interval to schedule and the time of day to start the batch job.
- In the Calculate Future Time on Schedules option, click Schedule Batch to schedule the batch calculation of Future Scheduled Hours.