Schedule
Config Key: asm.base.schedule
Settings for Schedules
auto-recalculate-schedule-for-assignments |
Boolean |
Determines whether schedules are recalculated for all related assignments when project tasks or project task assignments have been modified. The default value is true. |
true
|
auto-recalculate-schedule-for-held-resource-requests |
Boolean |
Determines whether schedules are recalculated for all related held resource requests when project tasks or project task assignments have been modified. The default value is true. |
true
|
schedule-queue-batch-size |
Number |
Number of schedule ids in a batch when calculating scheduled days and hours |
2000
|
|