Configuring Bottom-Up Planning

Bottom-Up Planning comprises a set of pages, objects and settings that allow you to build out project plans from the project task level through resource requests to eventual assignments. You can adjust the following settings and validation rules to customize the process to suit your approach.

Configuration Options Affecting Bottom-Up Planning

Configuration Group

Configuration Option

Description
Resource Requests allow-to-assign-a-resource-with-different-role allow-to-assign-a-resource-with-different-role
auto-update-pta-with-assigned-resource auto-update-pta-with-assigned-resource
auto-update-pta-with-held-resource auto-update-pta-with-held-resource
auto-update-rr-with-assigned-resource
auto-update-rr-with-assigned-resource
create_RR_only_where_all_info_available_on_PTA create_RR_only_where_all_info_available_on_PTA
create-rr-if-pta-not-having-resource-when-create-assignment create-rr-if-pta-not-having-resource-when-create-assignment
ignore-pta-not-having-resource-when-create-assignment ignore-pta-not-having-resource-when-create-assignment
default-resource-role default-resource-role
pta_fieldset_to_split _resource_request pta_fieldset_to_split _resource_request

Validation Rules Affecting Bottom-Up Planning

Parent Object Validation Rule Action Rationale
Project Task Assignment Resource_Or_External_Resource_Required Deactivate In a task-based approach to project planning, users may want to assign a role, rather than an internal or external resourceClosed A person or entity that is external to your Salesforce organization. You can use external resources when assigning external staff, such as contractors, to project tasks., to a project task. If enabled, this validation rule will prevent them from doing so.

Link to Assignments

You can configure PSA to update source project task assignment records with the resource that you eventually assign to a task-driven resource requestClosed Describes a resource request that has been generated based on information on project tasks and their associated project task assignments. If you use a task-based approach to manage your projects, you can generate task-driven resource requests on the Generate Resource Requests From Project Task Assignments page (accessed from Project Task Gantt, Gantt or the Project detail record).. This ensures consistency between resources assigned to project tasks and resources assigned to regular assignments downstream. If you have assigned external resourcesClosed A person or entity that is external to your Salesforce organization. You can use external resources when assigning external staff, such as contractors, to project tasks. to project tasks, using either Project Task Gantt, Gantt or the standard Salesforce interface, they are automatically removed when you come to assign a resource to a task-driven resource request. For more information, see auto-update-pta-with-assigned-resource.

Permissions Required for Bottom-Up Planning

Grant users the Resource Request Entry permission control and edit access for the relevant fields to allow them to generate resource requests based on project tasks. For more information, see Permission Control Fields.