Zooming and Fitting on the Timeline

Zooming on the Timeline

You can change the level of detail at which records display by zooming in or out of the timelineClosed A feature of the Resource and Project Planners. Offers a visual overview – in days, weeks, months or quarters – of assignment duration and scheduled hours, as well as total hours rolled up to the parent resource or project.. You can use zoom to:

To zoom the timeline:

  1. Click the down arrow on the Zoom picklist.
  2. Select Day, Week, Month or Quarter to view the timeline at the level you want.

Fitting the Timeline

Click Fit to snap your view of the timeline to fit all of the records.

Click Today to center the timeline on today's date, adjusting the zoom level if necessary.