Staffer Settings

You can control the PSA behavior for scheduling strategy using the settings in the Resource Staffer configuration groupClosed A collection of configuration options contained in the configuration groups tab that defines behavior of a PSA object or feature..

Field Description
DefaultSchedulingStrategy Default scheduling strategy for the Schedule Strategy field on the Assign Resource to Project page and the Assign Resource section of the Resource Request page. The default value is "Calculate End Date Level Schedule":
  • Calculate End Date, Level Schedule
  • Calculate End Date, Ignore Availability
  • Adjust Hours Per Day
  • Custom
  • Percent Allocation.
use-task-based-schedule-creation-strategy When true, the Task Based Schedule Creation strategy is used when creating task-driven resource requests and assignments. When task-driven assignments or held resource requests are created, the combined total task hours are split evenly across the available working days of a resource's calendar based on the task's start and end date. If false, the Adjust End Date strategy is used. The default value is false.