Creating a Project Task Hierarchy

You can create a project task hierarchy by creating child tasks underneath a parent or summary task:

  1. Display the project task to which you want to add a child task.
  2. Scroll to the Project Tasks (Child Task) related list.
  3. Click New Project Task.
  4. Complete the fields described in Project Task Fields.
  5. Click Save.
Note: Note
Points, percentages, and status checkbox fields are rolled up from child to parent fields as progress is made on project tasks.Points calculation fields on the parent project task reflect the child tasks.You cannot create a child task if the parent task already has an assignment.

Related Concepts

Project Tasks

Related Tasks

Starting, Updating and Completing a Project Task

Creating a Project Task on the New Project Task Page

Creating Preceding and Dependent Tasks

Assigning Resources to a Project Task

Reference

Project Task Fields

Project Task Assignment Fields

Project Task Dependency Fields

Project Task Points History

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.