Here is a description of the fields and buttons on a Project Task.
Key:
* – Mandatory field.
255 – maximum field length.
S – If the task is a summary task, information from child tasks is rolled-up to this field and you cannot edit it.
Field | Description | ||
---|---|---|---|
Actual End Date & Time | S | Date on which the task actually completed. This is the date on which the Completed checkbox was selected. | |
Actual Hours | S | Hours spent on the task rolled-up from the task time entry on the related timecard. Hours from child tasks are rolled-up to this field. | |
Actual Start Date & Time | S | Date on which the task actually started. This is the date on which the Started checkbox was selected. | |
Assigned Resources | System generated list of resources from the project/task assignment associated with the task. | ||
Assigned Resources (Long) | Resources assigned to the project taskA unit of work or collection of work associated with a project.. | ||
Blocked | Indicates whether there is something preventing this task from being completed. | ||
Completed | S | Indicates whether the task has been completed. | |
Do Not Auto Update Parents |
Indicates whether the parent project task is prevented from being updated when the points, dates and status fields are updated on this task. |
||
Do Not Auto Update this Task | Indicates whether updates to automatically calculated fields such as start and end dates, percentage complete and points are prevented. | ||
Duration Units | Specifies the units of time used for project tasks. Valid values are hours or days. The default value is days. | ||
End Date & Time | S | The date and time on which work for this task is projected to end. Timecards can still be entered for a task after this date as long as it is not closed for time entry. | |
Estimated Hours | Original estimated hours for the task. | ||
Estimated Time To Completion (Task) |
Specifies the estimated hours to completion (ETC) required to finish a project task. When a value is not specified, ETC is not used. When the value is zero, the task is considered complete. When any other value is entered, ETC is considered. For more information about how this field works in conjunction with other fields, see Hours Remaining, Percent Complete (Hours) and Projected Hours fields. |
||
Hours Remaining | Number of hours remaining to complete the task calculated from estimated hours minus actual hours. When a value is set in Estimated Time to Completion (Task), Hours Remaining is derived from Estimated Time to Completion (Task). | ||
Milestone | The milestone of the parent project. | ||
Notes | Notes on the project task. The content of this field is shared with the Project Task notes field on task lines in the Time Entry page. You can display this field in the Time Entry page by adding it to a task time field set. See Task Time Field Sets. | ||
Peer Order | Internal use only. | ||
Percent Complete (Hours) |
|
||
Percent Complete (Points) | S | The total number of completed project task points divided by total number of project task points related to this one. This includes child tasks. This field updates as the projectA collection of activities and related items to be managed over a defined time range, such as timecards, expenses, milestones and budgets. is completed. | |
Percent Complete (Tasks) | S | The total number of completed project tasks divided by total number of project tasks related to this one. This includes child tasks. This field updates as the project is completed. | |
Points | S | The burn-down points. For instance, you can assign a complex task a higher number of points than a simpler one. |
|
Points Baseline | S | Points allocated to the task. | |
Points Complete | S | Indicates the number of project task points that are completed. | |
Points Remaining | S | Indicates the number of project task points that are yet to be completed. | |
Priority | The current priority of the task. | ||
Project | Name of the project to which the project task relates. | ||
Project Task Name | * | 255 | The name representing the project task and its children if applicable. |
Projected Hours | S |
Formula field. The sum of Actual Hours and Estimated Time To Completion (Task). When Estimated Time to Completion (Task) is not set, the Projected Hours value uses and displays the value of the Estimated Hours field. |
|
Start Date & Time | S | The date and time on which work for this task is projected to start. Timecards can still be entered for a task before this date as long as it is not closed for time entry. | |
Started | S | Indicates whether the task has been started. | |
Status |
The status of the project task. Default values are Deferred, In Progress, and Aborted. |
||
Summary |
Indicates whether the task is a summary task. A summary contains at least one child task. Information from a child task such as start and end date, percentage complete and points rolls-up to its parent summary task. |
||
Timecard Hours | S | R | Total hours spent on the task. This rolls-up from task time entries on timecards. The value in this field is copied to the Actual Hours field, which then rolls-up the hierarchy. |
WBSWork Breakdown Structure Element Number | An identifier which you can use to link the task to an external task management system. |
Key: 255 or 32k – maximum field length.
Field | Description | |
---|---|---|
Description |
255 | Description for the project task. |
Long Description | 32k | Extended description for the project task. |
Key: 255 – maximum field length.
Field | Description | |
---|---|---|
Hierarchy Depth | Number of parent tasks to the top-level task. | |
Parent Task | The parent task of the project task. Enter a Parent Task only when you are changing the project task hierarchy. | |
Parent Task End Date | Parent task end date. | |
Parent Task End Date & Time | End date and time of the parent task. | |
Parent Task Start Date | Parent task start date. | |
Parent Task Start Date & Time | Start date and time of the parent task. | |
Task Key | Identifier of the task. | |
Task Key Chain | Delimited list of Task Keys in the project task hierarchy. | |
Task Name Chain | 255 | Delimited list of parent task names up to the top-level task. |
Task Name Chain API | This field has same behavior as the Task Name Chain field, but it is larger to accommodate a larger number of project tasks in the hierarchy. | |
Top-level Parent Task | The top-level parent task for the project task. The field is blank when the project task is a top-level task. |
Field | Description |
---|---|
External Task ID | An identifier which you can use to integrate the task with task management applications that do not run on the Salesforce platform. |
The following related lists, are displayed with the project task detail and are used to view and manage the project task details and attributes:
Button | Description |
---|---|
Start | Marks the task as started and sets the Actual Start Date and Time fields. |
Complete | Marks the task as complete and sets the Actual End Date and Time fields. |
Related Concepts
Task-Driven Resource Requests and Assignments Overview
Project Task Gantt (Task Manager)
Related Tasks
Generating Assignments from Tasks
Generating Resource Requests from Tasks
Starting, Updating and Completing a Project Task
Creating a Project Task Hierarchy
Creating a Project Task on the New Project Task Page
Creating Preceding and Dependent Tasks
Assigning Resources to a Project Task
Reference