Generating Assignments from Tasks

Note: Prerequisites
If the default_est_hours_on_task_RR_for_PTA setting in the Resource Requests configuration group is not defined, you must add estimated hours to tasks before you can create a project assignment from a project task assignment.

You must have been granted the Staffing permission control in order to generate assignments from tasks.
  1. Click Generate Assignments on the Project Tasks related list of the project detail page that you are generating assignments for. Project tasks must have one or more project task assignments.
    Or, on Project Task Gantt, click Create Resource Demand and then Create Assignments.
  2. Select some attributes to base the generated assignments on. You can only select Milestone together with Role, Resource, or External Resource. Custom attributes may be available to select if configured by your administrator.
  3. Optionally, in the Longest Gap Allowed (Days) field, enter the duration of the longest gap, including weekends, permitted between consecutive project task assignments before a single assignment is divided into two. To ignore weekends when calculating gap duration, select Ignore Saturdays or Ignore Sundays.
    Tip: Tip
    If you don't enter a value, the process ignores gaps in the task schedule and generates an assignment that spans the start and end dates of the source project task assignments.
  4. Click Preview Assignments.
  5. Preview the assignments, including scheduled hours, cost rate, bill rate, duration, and the proposed resource to be assigned.
    Tip: Tip
    The proposed quantity and field values of the assignments depend on which attributes you select. Try a combination that reflects how much information is on your project task assignments.
  6. Update any assignment fields that you can edit. Your administrator can set the use-task-based-schedule-creation-strategy setting to control this behavior.
  7. Use Update Preview and Reset Preview as described in Buttons.
  8. Deselect any previewed assignments that you want to discard.
  9. Click Generate to save the records to your organizationA deployment of the Salesforce/FinancialForce applications with a defined set of licensed users. Your organization includes all of your data and applications, and is separate from all other organizations.. The new task-generated assignments are displayed on the Unfilled Resource Requests page, along with summary information.
  10. Optionally, delete any assignments that you no longer want.
Note: Notes
If several project task assignments exist on the project with the same resource or role, these are combined to create a single assignment.
Project task assignments for which a resource role cannot be derived are ignored when generating assignments from tasks.
Combined project task assignments using the task based scheduling strategy resulting in the creation of an assignment or held resource request having more than 24 hrs for a day are ignored.

Resources who do not have roles matching a role for a project assignment can be included in a list of possible resources to assign to a project task assignment. Your administrator can set the allow-to-assign-a-resource-with-different-role setting to control this behavior.

Related Concepts

Task-Driven Resource Requests and Assignments Overview

Bottom Up Planning Examples

Bottom-Up Planning

Resource Requests

Project Task Gantt (Task Manager)

About Tasks

Reference

Generate Resource Requests, Held Resource Requests or Assignments from Project Tasks Fields

Unfilled Resource Requests Fields

Resource Request Fields

Project Task Fields

Project Task Assignment Fields