Bottom Up Planning Examples

Here are some examples of Bottom-Up Planning scenarios.

Generating Task-Driven Resource Requests

The following tables illustrate two scenarios where a set of project tasks is used to generate resource requests: firstly by Role and secondly by both Milestone and Role.

Table: Set of Project Tasks
Project Task Project Milestone Internal Resource External Resource Resource Role
Task 1 Milestone A     Developer
Task 1 Milestone A     Java Developer
Task 2 Milestone A     Consultant
Task 3 Milestone B Robert    
Task 4 Milestone D Daniel   Developer
Task 5 Milestone B Daniel    

 

Table: Scenario One—Resource Requests generated based on Role
Target Resource Request Resource Role Project Milestone Project Tasks
RR1 Developer Milestone A, Milestone D Task 1,
Task 4
RR2 Java Developer Milestone A Task 1
RR3 Consultant Milestone A Task 2
RR4 Robert's role on Contact record Milestone B Task 3
RR5 Daniel's role on Contact record Milestone B Task 5

 

Table: Scenario Two—Resource Requests generated based on Milestone and Role
Target Resource Request Resource Role Project Milestone Project Tasks
RR1 Developer Milestone A Task 1
RR2 Developer Milestone D Task 4
RR3 Java Developer Milestone A Task 1
RR4 Consultant Milestone A Task 2
RR5 Robert's role on Contact record Milestone B Task 3
RR6 Daniel's role on Contact record Milestone B Task 5

Generating Task-Driven Assignments

The following tables illustrate a scenario where a set of project tasks is used to generate assignments.

Table: Set of Project Tasks and duration
Project Tasks Resource Role Estimated PTA Hours Mon Tue Wed Thu Fri
Task 1 Project manager 12 Day 1 Day 2 Day 3    
Task 2 Project Manager 10 Day 1 Day 2 Day 3 Day 4 Day 5
Task 3 Project Manager 3         Day 1

As an example, Task 1 has a duration of three days (Day 1, Day 2 and Day 3), from Monday to Wednesday.

 

Table: Creation of schedule
Project Tasks Hours per Day Mon Tue Wed Thu Fri
Task 1 4 4 4 4    
Task 2 2 2 2 2 2 2
Task 3 3         3
  Scheduled Hours for Assignment 6 6 6 2 5

The 4 hours per day for Task 1 from Monday to Wednesday are derived from the estimate of 12 hours divided by the 3 day duration of the task, (Day 1, Day 2 and Day 3).

Setting Longest Gap Allowed

You can set how long to allow between consecutive project task assignments before FinancialForce PSA generates separate resource requests or assignments based on your selected attributes. The following tables illustrate a scenario.

You created two project tasks on a project and assigned two Architect roles to the tasks.

Table: Consecutive Project Task Assignments
Project Task Assignment Project Task Resource Role Project Task Start Date Project Task End Date
PTA-652 Planning Architect 04/28/2014 04/30/2014
PTA-677 Implementation Architect 06/28/2014 06/30/2014

On the Generate Resource Requests from Project Task Assignments page, you preview resource requests based on Role but do not specify a value for Longest Gap Allowed (Days). One resource request is shown:

Table: Task-Driven Resource Requests; No Gap
Resource Role Start Date End Date
Architect 04/28/2014 06/30/2014

Architects are not required to work on the project from May through end of June 2014. Therefore:

  1. You click Reset to discard the previewed resource requests.
  2. You select Role and enter 10 for Longest Gap Allowed (Days), but do not select Ignore Saturdays or Ignore Sundays.
    The resource request for an Architect is split into two:
Table: Task-Driven Resource Requests; 10 Day Gap
Resource Role Start Date End Date
Architect 04/28/2014 04/30/2014
Architect 06/28/2014 06/30/2014

Field Mappings

The following tables summarizes the mappings used to generate task-driven resource requestsDescribes a resource request that has been generated based on information on project tasks and their associated project task assignments. If you use a bottom-up approach to manage your projects, you can generate task-driven resource requests on the Generate Resource Requests From Project Task Assignments page (accessed from Project Task Gantt or the Project detail record). .

Key: * – Mandatory field.

Resource Request Field   Project Task Field Project Task Assignment Field Resource Field
Start Date   - Project Task Start Date lookup -
End Date   - Project Task End Date lookup -
Notes   - Resource (if attribute(s) other than Resource are selected on generation page) -
Requested Hours   Sum of Duration (Hours) field on all project tasks. - -
Role * - Resource Role (first choice mapping) Resource Role (second choice mapping if role unspecified on project task assignment)
Suggested Resource * - Resource -

Use Task Based Schedule Creation Strategy Setting

Depending on a true or false value of the use-task-based-schedule-creation-strategy setting, fields are read-only or editable in the Edit, Save or Discard sections of the following previews:

The following table shows which fields are editable or read-only.

Key:
R = Read-only.
E = Editable.

Field Edit, Save or Discard Preview Generate Sections
Setting True Setting False
RR Held RR Asn RR Held RR Asn
Resource Role E E E E E E
Requested Hours E R R E E E
Scheduled Hours E R R E E E
Requested Bill Rate E E E E E E
Start Date E E R E E E
End Date E E R E R R

Related Tasks

Generating Assignments from Tasks

Generating Resource Requests from Tasks

Creating Resource Demands from Project Task Gantt

Viewing Summary Information

Reference

Generate Resource Requests, Held Resource Requests or Assignments from Project Tasks Fields

Unfilled Resource Requests Fields

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.