Here are some examples of Bottom-Up Planning scenarios.
The following tables illustrate two scenarios where a set of project tasks is used to generate resource requests: firstly by Role and secondly by both Milestone and Role.
Project Task | Project Milestone | Internal Resource | External Resource | Resource Role |
---|---|---|---|---|
Task 1 | Milestone A | Developer | ||
Task 1 | Milestone A | Java Developer | ||
Task 2 | Milestone A | Consultant | ||
Task 3 | Milestone B | Robert | ||
Task 4 | Milestone D | Daniel | Developer | |
Task 5 | Milestone B | Daniel |
Target Resource Request | Resource Role | Project Milestone | Project Tasks |
---|---|---|---|
RR1 | Developer | Milestone A, Milestone D | Task 1, Task 4 |
RR2 | Java Developer | Milestone A | Task 1 |
RR3 | Consultant | Milestone A | Task 2 |
RR4 | Robert's role on Contact record | Milestone B | Task 3 |
RR5 | Daniel's role on Contact record | Milestone B | Task 5 |
Target Resource Request | Resource Role | Project Milestone | Project Tasks |
---|---|---|---|
RR1 | Developer | Milestone A | Task 1 |
RR2 | Developer | Milestone D | Task 4 |
RR3 | Java Developer | Milestone A | Task 1 |
RR4 | Consultant | Milestone A | Task 2 |
RR5 | Robert's role on Contact record | Milestone B | Task 3 |
RR6 | Daniel's role on Contact record | Milestone B | Task 5 |
The following tables illustrate a scenario where a set of project tasks is used to generate assignments.
Project Tasks | Resource Role | Estimated PTA Hours | Mon | Tue | Wed | Thu | Fri |
---|---|---|---|---|---|---|---|
Task 1 | Project manager | 12 | Day 1 | Day 2 | Day 3 | ||
Task 2 | Project Manager | 10 | Day 1 | Day 2 | Day 3 | Day 4 | Day 5 |
Task 3 | Project Manager | 3 | Day 1 |
As an example, Task 1 has a duration of three days (Day 1, Day 2 and Day 3), from Monday to Wednesday.
Project Tasks | Hours per Day | Mon | Tue | Wed | Thu | Fri |
---|---|---|---|---|---|---|
Task 1 | 4 | 4 | 4 | 4 | ||
Task 2 | 2 | 2 | 2 | 2 | 2 | 2 |
Task 3 | 3 | 3 | ||||
Scheduled Hours for Assignment | 6 | 6 | 6 | 2 | 5 |
The 4 hours per day for Task 1 from Monday to Wednesday are derived from the estimate of 12 hours divided by the 3 day duration of the task, (Day 1, Day 2 and Day 3).
You can set how long to allow between consecutive project task assignments before FinancialForce PSA generates separate resource requests or assignments based on your selected attributes. The following tables illustrate a scenario.
You created two project tasks on a project and assigned two Architect roles to the tasks.
Project Task Assignment | Project Task | Resource Role | Project Task Start Date | Project Task End Date |
---|---|---|---|---|
PTA-652 | Planning | Architect | 04/28/2014 | 04/30/2014 |
PTA-677 | Implementation | Architect | 06/28/2014 | 06/30/2014 |
On the Generate Resource Requests from Project Task Assignments page, you preview resource requests based on Role but do not specify a value for Longest Gap Allowed (Days). One resource request is shown:
Resource Role | Start Date | End Date |
---|---|---|
Architect | 04/28/2014 | 06/30/2014 |
Architects are not required to work on the project from May through end of June 2014. Therefore:
10
for Longest Gap Allowed (Days), but do not select Ignore Saturdays or Ignore Sundays.Resource Role | Start Date | End Date |
---|---|---|
Architect | 04/28/2014 | 04/30/2014 |
Architect | 06/28/2014 | 06/30/2014 |
The following tables summarizes the mappings used to generate task-driven resource requestsDescribes a resource request that has been generated based on information on project tasks and their associated project task assignments. If you use a bottom-up approach to manage your projects, you can generate task-driven resource requests on the Generate Resource Requests From Project Task Assignments page (accessed from Project Task Gantt or the Project detail record). .
Key: * – Mandatory field.
Resource Request Field | Project Task Field | Project Task Assignment Field | Resource Field | |
---|---|---|---|---|
Start Date | - | Project Task Start Date lookup | - | |
End Date | - | Project Task End Date lookup | - | |
Notes | - | Resource (if attribute(s) other than Resource are selected on generation page) | - | |
Requested Hours | Sum of Duration (Hours) field on all project tasks. | - | - | |
Role | * | - | Resource Role (first choice mapping) | Resource Role (second choice mapping if role unspecified on project task assignment) |
Suggested Resource | * | - | Resource | - |
Depending on a true or false value of the use-task-based-schedule-creation-strategy setting, fields are read-only or editable in the Edit, Save or Discard sections of the following previews:
The following table shows which fields are editable or read-only.
Key:
R = Read-only.
E = Editable.
Field | Edit, Save or Discard Preview Generate Sections | |||||
---|---|---|---|---|---|---|
Setting True | Setting False | |||||
RR | Held RR | Asn | RR | Held RR | Asn | |
Resource Role | E | E | E | E | E | E |
Requested Hours | E | R | R | E | E | E |
Scheduled Hours | E | R | R | E | E | E |
Requested Bill Rate | E | E | E | E | E | E |
Start Date | E | E | R | E | E | E |
End Date | E | E | R | E | R | R |