Field   Description
Work Calendar Name * Name of the work calendar.
Allow Start/End on Non-working Days   If true, task start and end dates can extend into non-working time.
Week Start Day   First work day of your week.
Monday Hours   Default number of hours to be worked on each day. Used to create a new resource schedule. A value of null is treated as a zero-hour (non-working) day.
Tuesday Hours  
Wednesday Hours  
Thursday Hours  
Friday Hours  
Saturday Hours  
Sunday Hours  
Monday Start Hour   The hour of day a work schedule starts. Values are picklist entries specified as hh:mm (label) where hh is the hour, mm is the minutes and (label) is a user-friendly label to display. The time period starts at 00:00 as midnight and goes to 23:50 as 11:50 pm. The smallest supported increments of time are 10 minute increments. By default, entries are listed in half-hour increments throughout a 24-hour period.
Tuesday Start Hour  
Wednesday Start Hour  
Thursday Start Hour  
Friday Start Hour  
Saturday Start Hour  
Sunday Start Hour  
Monday End Hour   The hour of day a work schedule ends. Values are picklist entries specified as hh:mm (label) where hh is the hour, mm is the minutes and (label) is a user-friendly label to display. The time period starts at 00:00 as midnight and goes to 23:50 as 11:50 pm. The smallest supported increments of time are 10 minute increments. By default, entries are listed in half-hour increments throughout a 24-hour period.
Tuesday End Hour  
Wednesday End Hour  
Thursday End Hour  
Friday End Hour  
Saturday End Hour  
Sunday End Hour  
Week Total Hours R Calculated from day of the week entries.
Standard Hours Per Day   Typical number of hours in a working day.

Related Concepts

About Time Periods, Work Calendars and Holidays

Project Task Gantt (Task Manager)

Related Tasks

Setting up Work Calendars

Creating or Importing Time Periods

Reference

Project Task Fields

Project Task Dependency Fields

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.