Adding a Task or Checkpoint

You can add a project taskA unit of work or collection of work associated with a project. or a checkpointZero day task record, which is used to represent an event in the project such as a key decision, completion of a work package, completion of a deliverable or end of a phase. Checkpoint tasks have no relationship with PSA milestones. to a projectA collection of activities and related items to be managed over a defined time range, such as timecards, expenses, milestones and budgets. using the Tasks pane or the Context menu.

To add a project task or checkpoint to a project using the Tasks pane:

  1. Select the project to which you want to add a task.
  2. Select a task on the Schedule or Task pane under which you want the new task to appear.



  3. Click Create New Task to add the task to the Schedule pane.
  4. Enter a name for the task.
  5. Select or enter the Start and End dates of the task.
  6. [Optional] Enter a duration in the Duration cell.
    Tip: Tip
    If you want a checkpoint, set the duration to zero days.
  7. [Optional] In the Points cell, enter the estimated effort, in points, required to complete the task.
    Note: Note
    You must ensure that the Points field contains a number greater than or equal to zero. If you use planning pokerA consensus based technique commonly used in Agile software development for estimating the size or relative effort of a task or story. to estimate effort or the relative size of a task, we recommend entering a number in the Fibonacci sequenceA sequence of whole numbers where the first numbers in the sequence are 0, 1, 2 and every subsequent number in the sequence is the sum of the previous two numbers. such as 0, 1, 2, 3, 5, 8, 13, 21, 34, 55 or 89.
  8. If you want to assign one or more resources or roles to the task:
    1. Click the Assigned Resources cell.
    2. Click Add another resource.
    3. Select the name of the resource or enter some characters from their name. You can assign a resource who is external to your PSA organization (an external resource): enter their name, press Enter or click OK, and click Assign when the Confirm External Resource popup window appears.
    4. Select a Resource Name cell and select an option in the drop-down list from those available in your organization.
    5. Repeat the step above for the role you want.
    6. Add more resources and roles if required.
    7. Click Apply Changes.
    8. Note: Note
      This action creates a project task assignment not a resource assignment. Depending on the configuration that your administrator has chosen, resources can enter time against this project task. If you want the resource to book time and expenses to the project, you must also assign them to the project. See Searching for Resources and Entering Time Against Project Tasks.
  9. If you want to associate the project task with a milestone on the project:
    1. Click the Milestone cell.
    2. Select a milestone from the drop-down list.
  10. Click Save.

To add a project task or checkpoint using the context menu:

  1. Select the project to which you want to add a task.
  2. Right-click a task in the Task pane or the Schedule pane or right-click the bottom of either pane.
  3. Hover over Add and then do one of the following:
  4. Enter a name for the task and complete the remaining fields in the Tasks pane.
  5. Click Save.

Related Concepts

Project Task Gantt (Task Manager)

About Tasks

About Task Dependency Relationships and Lag

Task-Driven Resource Requests and Assignments Overview

Resource Requests

Related Tasks

Managing Projects

Viewing Tasks

Viewing Task Details

Changing Start and End Dates

Adding a Task Dependency Relationship

Deleting a Task Dependency Relationship

Editing a Task Dependency Relationship

Assigning Resources or Roles to a Project Task

Closing Project Task Gantt

Deleting Tasks

Editing Project Task Details

Moving Tasks

Printing the Project Plan

Saving Changes

Searching

Undoing and Redoing Changes

Viewing the Critical Path

Zooming

Creating Resource Demands from Project Task Gantt

Associating Project Tasks with Milestones

Configuring Alerts and Restricted Editing of Project Task Constraints

Using Task Notes in Project Task Gantt

Setting up Work Calendars

Reference

Project Task Gantt Fields

Project Task Gantt Settings and Preferences

Generate Resource Requests, Held Resource Requests or Assignments from Project Tasks Fields

Resource Request Fields

Project Task Fields

Project Task Assignment Fields

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.