You can edit project tasks in the Task pane or the Schedule pane. Changes that you make on the Schedule and Task panes are shown immediately so that you can view the effect of your changes before saving them. Changes are not saved until you click Save. For more information, see Project Task Gantt Fields.
You can edit the Task Name, Points, Points Complete, Points Remaining, Percentage Complete, Estimated Hours, Hours Remaining, Assigned Resources and Roles, Milestone, Start Date and End Date fields inline or you can edit the fields on the Task Editor popup. Fields that you are unable to edit are shaded gray on the Tasks pane.
You can restrict editing of Task-related field sets by designating specific field sets as read-only. For more information, see Project Task Gantt Settings and Preferences.
To edit the details of a project taskA unit of work or collection of work associated with a project. inline:
To view and edit the details of project tasks using the Task Editor popup:
To change the name of a task:
To edit the duration:
Indicators in Project Task Assignments assume:
A basic error condition causing Project Task Assignment indicators to display are when the sum of all task hours associated with an Assignment exceeds the scheduled hours on the Assignment.
Red Alert Indicator Conditions
Project Task Assignment Dates | The Task has Project Task Assignments with at least one of the Project Task Assignments having dates within the Assignment's time period. | ||
And: | |||
None of the Project Task Assignment date ranges overlap with the Parent Task dates. | |||
Project Task Assignment Hours | The Task has defined (zero or more) estimated hours. | ||
And: | |||
The Task has one Project Task Assignment with associated dates. | |||
And: | |||
One of the following conditions is true: | The total Task hours per Project Task Assignment exceed the scheduled hours for the Assignment. | ||
The Task hours exceed the total scheduled hours for the Assignment for all Project Task Assignments included in the Assignment. | |||
The total estimated task hours for all Project Task Assignments with an associated Resource Request exceed either: |
|||
The scheduled hours of a held Resource Request. | |||
The requested hours for an unheld Resource Request. |
Yellow Alert Indicator Conditions
Project Task Assignment Dates | A Task has no Project Task Assignments. | |
And: | ||
The Task dates do not qualify for a red alert indicator condition. | ||
And: | ||
A Task has Project Task Assignments but: | None of the Project Task Assignments have dates. | |
Or: | ||
The Project Task Assignments have dates that partially cover task dates but there is at least one day within the Task date range that does not fall within any Project Task Assignment date ranges. | ||
Project Task Assignment Hours | The Task has more than zero estimated hours. |
|
And: | ||
The Project Task Assignment hours do not qualify for a red alert indicator condition. | ||
And: | ||
One of the following is true: | ||
The sum of all Task hours associated with an Assignment exceeds the scheduled hours on the Assignment. When multiple Project Task Assignments are associated with a Task, the total Project Task Assignment hours on the Task are calculated by taking the sum of all the Project Task Assignment hours and dividing them equally by the number of Project Task Assignments. |
||
Or: | ||
The Task has no Project Task Assignments with Assignments or has no associated Resource Requests. |
No Alert Flags:
The Project Task Assignment's total 30 hours is less than the Assignment's scheduled 40 hours.
Red Alert Flag:
The Project Task Assignment hours total of 55 exceed the Assignment's scheduled 40 hours.
Yellow Alert Flag:
When calculating the total hours for the Project Task Assignments, any task with multiple Project Task Assignments is the total hours shared equally among the number of Project Task Assignments. The total calculated hours is 45 hours (20 for the first task + 20 for the second task + 5 hours for the third task's 10 hours divided by two Project Task Assignments).
The Project Task Assignment hours total of 45 exceed the Assignment's scheduled 40 hours. With multiple Project Task Assignments associated with the task, the distribution of hours is ambiguous and the entry is flagged with a Yellow alert.
Related Concepts
Project Task Gantt (Task Manager)
About Task Dependency Relationships and Lag
Related Tasks
Adding a Task Dependency Relationship
Deleting a Task Dependency Relationship
Editing a Task Dependency Relationship
Assigning Resources or Roles to a Project Task
Creating Resource Demands from Project Task Gantt
Associating Project Tasks with Milestones
Configuring Alerts and Restricted Editing of Project Task Constraints
Using Task Notes in Project Task Gantt
Reference