Swapping Assignments and Held Resource Requests

To manage changes to project schedules in Resource and Project Planners, you can swap resources on:

Note:

Your administrator is able to determine whether users can swap assignments with a start date set in the past. For more information, see Restrict Swapping Past Dates in Resource and Project Planners Settings and Preferences.

You cannot swap:

To swap a resource on an assignment or held resource request:

  1. In Resource and Project Planners, select an assignment or resource request.
  2. Click Swap Resource.
  3. Select a resource from the New Resource drop-down In the Swap Assignment dialog.
  4. Click Swap.
  5. Click Save.