Resourcing Lightning Component Fields

The Resourcing component enables you to select from a list of resources to:

Resources with contact records that have the following set to true are displayed:

Resources Fields

The following fields are displayed:

Key: R - Read-only.

Field

 

Description
% Availability  

The percentage availability value for each resource.

This value is calculated from a resource’s scheduled hours in the search period [Start Date and End Date fields in the PSA Resource Filter Lightning component] divided by available hours based on the resource's work calendar multiplied by 100.

Whole numbers are displayed. When a resource is completely available, 100 is displayed. If a resource is utilized, 100 decreases until 0 is displayed. When a resource is over-allocated, a negative value is displayed. When availability data is not available for a resource, the value is blank. For example, when the start and end dates are in the past.

Note:

If you cannot see the % Availability column, or the values in it for each resource, you might need permissions for the Work Calendar and Utilization Engine objects. For more information, see Resource Request Lightning Page and Component Permissions.

Cost Rate   The currency and cost rate for the resource.
External   Indicates whether the resource is external to your business, for example, a contractor.
Projected End Date R The projected end date of the new schedule to be created for the selected resource based on the projected start date and the selected strategy. Click Refresh End Date to update this field and reflect the custom hours you have entered for the schedule when the Custom scheduling strategy is selected.
Projected Start Date R The projected start date of the new schedule to be created for the selected resource based on the projected start date and the selected strategy.
Rank  

This column is displayed in the PSA Resourcing component when Include Recommended Resources is selected. Rank is a numerical ranking for resources calculated using resource role, region, practice, group, skills ratings, and availability.

Suggested, held, and assigned resources are always ranked at the top of the results.

When the Rank column is displayed, resources are automatically sorted in rank ascending order, from 1 as the highest ranked to 200 as the lowest ranked.

For more information about how the rank is calculated, see Intelligent Staffing Overview and see Resource Search Service Settings.

Region   The region as specified on the resource's contact record that the resource is assigned to.
Requested Hours R Requested amount of hours for the selected resource as specified on the resource request.
Role   The role of the resource as specified on the resource's contact record.
Scheduling Strategy  

The scheduling strategy that determines how the requested hours are allocated across the resource'sClosed A contact that works on a project. schedule when holding or assigning a resource. For more information about scheduling strategies, see the Schedule table.

Status  

The status of the resource:

  • Assigned
  • Held
  • Suggested

When a suggested resource becomes held or assigned, the relevant status of "Held" or "Assigned" is displayed. Held and assigned resources always display at the top of the resource list.

Resourcing Component Buttons

The following buttons are available on the Resourcing component.

Button

Description

More Information
Assign Creates an assignment for the selected resource. Creating Assignments
Compare Opens the Compare Resources window. Comparing Resources
Hold Holds the selected resource against the resource request. Holding Resources
Manage Schedule Opens the window to manage a resource's schedule. Manage Schedule
Pin Pin a selected resource in the resource list. Pinning Resources
Unhold Unholds the selected resource from the resource request. Unholding Resources
Unpin Unpin a selected resource from the resource list. Pinning Resources

Manage Schedule

The following are available when you click Manage Schedule.

Tab Description More Information
Schedule

Select a strategy from the Scheduling Strategy picklist. The Projected Start Date and Projected End Date fields display for the new schedule to be created for the selected resource. These are based on the selected scheduling strategy and the start and end dates from the filter criteria.

The Total field displays the aggregated number of requested hours when you use the Custom scheduling strategy for the resource. For all other scheduling strategies, the Requested Hours field displays the total hours for the selected resource as specified on the resource request.
Viewing or Editing Projected Schedules of Resources