Change Requests

Once a purchase contract is approved and activated, the only way you can modify it is by creating a change request. A change request is a copy of an active purchase contract on which you can propose changes. Once you approve and apply a change request, the proposed changes are applied to the original contract. This enables you to modify and adjust your active contracts over time and offers you a version control system that helps you keep track of all changes applied. Existing change requests for a purchase contract are listed on the Change Requests related list of the contract. From this related list you can create new change requests and manage the existing ones. For more information, see Creating a Change Request.

When you create a change request for a purchase contract, a new purchase contract of type Change Request is created. In this process, all the field values of the original purchase contract are copied to the new change request record. The change request fields are prepopulated with the values of the original contract. You can modify these values as needed.

A copy of each line on the original contract is also created. You can propose changes to the original lines by editing their corresponding copies on the change request. You can also add new lines if required. The changes you make to existing lines and any new lines that you create are added to the original contract once the change request is approved and applied. Deleting existing lines is also possible, although these lines will become expired lines on the original contract after applying the changes. For more information see, Deleting Purchase Contract Lines

Each change request that you create is associated with its original purchase contract. In the same way, each change request line which is copied from the original contract is associated with its original line. Similarly, each new change request and each change request line are associated with their preceding change request and change request line respectively.

When you apply a change request to a purchase contract, all the changes included in the change request are applied to the active original contract and its lines. The applied change request is deleted and a new superseded change request containing the original purchase contract data, as it was before the changes, is created. This enables you to have detailed control over the changes made to a purchase contract through its subsequent versions.

What Happens When You Apply a Change Request?

Applying a change request only requires you to click Apply on an approved change request. However, there are several processes and changes that take place when you apply a change request to a purchase contract:

Diagram showing how a change request is created and applied.

Change Request Workflow

The change request workflow is as follows:

  1. Change request is created.
  2. Change request is approved.
  3. Change request is applied to the original purchase contract.