You can use the field sets contained on the Project Task and Project Task Assignment objects to customize the Create Project From Template page and Project Task Gantt. You can also change available fields when replacing resources on a project task assignment.
Additionally, field sets on the Project Task, Project Task Assignment, and Project Task Dependency objects define fields that require an edit lock, obtained by editing the project in Project Task Gantt or in standard Salesforce pages, in order to edit. These field sets are for internal use and should never be changed.
Key: L – Relates to project edit locking—see "Project Edit Locking Overview".
Field Set | Description | Used on Page | Default Fields | |
---|---|---|---|---|
|
Allows you to define the Project Task fields (if associated project tasks exist) that are copied from the project template to the new project. These fields do not display on the CreateProjectFromTemplate Visualforce page. | N/A | None. | |
|
Allows you to define the columns that display information in the Project Tasks section of the Create Project page when creating a project from a template. | Create Project from Template | Project Task Name; Status; Parent Task; WBS Element Number; Points; Start Date & Time ; End Date & Time; Description. | |
|
Fields that are in this field set are made available as additional columns on the tasks pane of Project Task Gantt. The API name of the field set must be referenced by the "Columns Field Set" setting. Currently, do not include the Parent Task Name in the custom columns. |
Project Task Gantt | None. | |
|
Defines fields that are always read-only on Project Task Gantt, regardless of a user's Field-Level Security settings. | Project Task Gantt | Actual Hours | |
|
L | Contains default fields on the project task that can only be edited if the user has an edit lock for the parent project. | Various | Start Date; End Date; Points; Parent Task; WBS Element Number; Milestone. |
Key: L – Relates to project edit locking—see "Project Edit Locking Overview".
Key: L – Relates to project edit locking—see "Project Edit Locking Overview".
Field Set | Description | Used on Page | Default Fields | |
---|---|---|---|---|
Require Lock For Editing | L | Contains default fields on the project task dependency that can only be edited when you have an edit lock for the parent project. | Various | Type; Preceding Task; Lag Time (Hours); Cross Project. |