Generating Assignments from Tasks
To generate assignments from tasks:
- Click Generate Assignments on the Project Tasks related list of the project detail page that you are generating assignments for. Project tasks must have one or more project task assignments.
Or, on Project Task Gantt, click Create Resource Demand and then Create Assignments. - Select some attributes to base the generated assignments on. You can only select Milestone together with Role, Resource, or External Resource. Custom attributes may be available to select if configured by your administrator.
- [Optional] In the Longest Gap Allowed (Days) field, enter the duration of the longest gap, including weekends, permitted between consecutive project task assignments before a single assignment is divided into two. To ignore weekends when calculating gap duration, select Ignore Saturdays or Ignore Sundays.
- Click Preview Assignments.
- Preview the assignments, including scheduled hours, cost rate, bill rate, duration, and the proposed resource to be assigned.
- Update any assignment fields that you can edit. Your administrator can set the use-task-based-schedule-creation-strategy setting to control this behavior.
- Use Update Preview and Reset Preview as described in Buttons.
- Deselect any previewed assignments that you want to discard.
- Click Generate to save the records to your organizationA deployment of the Salesforce/FinancialForce applications with a defined set of licensed users. Your organization includes all of your data and applications, and is separate from all other organizations.. The new task-generated assignments are displayed on the Unfilled Resource Requests page, along with summary information.
- [Optional] Delete any assignments that you no longer want.