Project Task Gantt Overview

If you are the project manager of a project, or have been assigned the Project Task Gantt Edit permission control, you can edit the tasks in your project using Project Task Gantt. Your administrator can restrict project manager access, as required by your organization. For more information, see the Project Manager Access setting in Project Task Gantt Settings and Preferences.

Project Task Gantt comprises the following panes:

  • The Tasks pane lists all the project tasks in your project.
  • The Schedule pane represents project tasks, checkpoint tasks, and the critical path for the project using graphical bars and elements.

Example Project Task Gantt

Here is an example of Project Task Gantt:

Example Tasks Pane

Here is an example of the Tasks pane:

Example Schedule Pane

Here is an example of the Schedule pane:

Schedule Pane Summary Overlay

Your administrator can define custom field sets to display tooltips for Milestones, Projects, Project Task Assignments, and Tasks in the Schedule pane of Project Task Gantt. For more information, see Project Task Gantt Settings and Preferences.