Edit dialog "chad".  Click "More" to change edit mode. Counter window. In Total hours held constant mode displays saved and current end date. Click "more" to view the saved and current start date and hours. Double-click on a cell to edit. Use the tab or right-arrow key to navigate to the right. Use Ctrl+Tab or the left-arrow key to move to the left. Counter window. In End date held constant mode displays saved and current hours. Click "more" to view the current and saved start date and end date. Edit dialog "chad".  Click "more" to change edit mode. Double-click on a cell to edit. Use the tab or right-arrow key to navigate to the right. Use Ctrl+Tab or the left-arrow key to move to the left.

Rapid Edit Overview

How it Works

Use rapid edit (also known as "Inline Editing") to edit in the Timeline panel in Resource and Project Planners.

You can edit hours in either of the following modes:

Note: Note
Rapid Edit in Resource and Project Planners using Total hours held constant mode is not compatible with schedules that were initially created using a zero-hour pattern. You can switch to End date held constant mode to make changes to schedules.

Edits apply to time periods based on the zoom level. When you edit a cell in the Week zoom level, the change applies to the week (or portion of a week) represented by the cell you edit.

To get started, review the following screenshots and see Editing in the Timeline (Rapid Edit).

At a Glance

Hover over an area for information about what it does.

Note: Note
Rapid Edit and Stretching Assignments in Resource and Project Planners uses the underlying schedule to allocate hours for remaining days on an assignment. Schedule exceptions due to holidays are integrated into the schedule using Work Calendar holidays.

All schedule exceptions for holidays are designated on the day level, not the hour level in Resource and Project Planners. Any day in a work calendar with more than zero hours counts as a "working day" in Planners and is allocated hours when making changes to the timeline.

Notes on Editing in Total Hours Held Constant Mode

When editing schedules in Total Hours Held Constant mode, schedule changes at the Week, Month, and Quarter zoom levels may appear not to work if you edit the last cell of an assignment.

For example:

In the above example, the assignment schedule in the last cell has 16 hours.

In the above example, this is the assignment schedule in Day zoom. Note the 16 hours in Week zoom level shows as two 8 hour days.

In the above example, the 16 hour schedule is changed to 10 hours in the Week zoom level using Total Hours Held Constant mode.

In the above example, after the change to the last cell, the schedule still shows 16 hours.

In the above example, viewing in Day zoom level, the ten hours show as two 5 hour days (Monday and Tuesday in the week of Sun 28 2015). The remaining six hours are added to a 6 hour day.

As a best practice, we recommend making changes in the Day zoom level when reducing hours in the last cell of an assignment.

Related Concepts

Resource Planner and Project Planner

At a Glance: Project Planner

At a Glance: Resource Planner

Edit Assignments Panel Overview

Filters Panel Overview

Working with the Edit Assignments Panel

Working with the Timeline

Related Tasks

Editing in the Timeline (Rapid Edit)

Reference

Resource and Project Planners Settings and Preferences

© Copyright 2009-2018 FinancialForce.com, inc. All rights reserved.
Various trademarks held by their respective owners.