Project Edit Locking Overview

When your administrator has enabled project edit locking, only one user at a time can edit project tasks, and their assignments (PTAs) and dependencies. The lock does not apply to other project-related objects such as assignments, resource requests, or schedules.

The lock is only applied when project task objects are being edited in Project Task Gantt, plus Gantt or Salesforce. The lock is not active when only Gantt and Salesforce are being used.

Your administrator must have:

Regardless of configuration, projects are unlocked after four minutes of inactivity.

If locking is enabled, a message informs you if another user is editing the same project tasks, assignments, or dependencies: