Task-Driven Resource Requests and Assignments Overview

Task-Driven Resource Requests

Task-driven resource requests are generated by FinancialForce PSA, based on attributes you select, from project tasksA unit of work or collection of work associated with a project. and child project task assignmentsAssociates a resource or a role with a project task for a defined time period. Use Project Task Gantt to assign resources or roles to project tasks.. They give you an informed estimate of the roles, resources, and project milestones you'll need to cover to deliver a project.

You can choose whether to generate unheld or held resource requestsOccurs when a named resource has been reserved (held) against, but not booked to, a project or opportunity. Also referred to as "soft booking".. Project task assignments need an allocated resource in order to generate held resource requests. Held resource requests are generated with a preferred schedule based on the work calendar associated with the held resource. This schedule is set with the "Calculate End Date, Ignore Availability" scheduling strategy.

Task-Driven Assignments

Task-driven assignments are generated by FinancialForce PSA, based on attributes you select, from project tasks and child project task assignments. They are created directly—without intermediate resource requests—and use the resource's default cost rate and a zero bill rate. Assignment hours are summed up from estimated hours on project tasks.

About Staffing

Requirements

The process requires source project tasks to exist on the project. You can create the project tasks in Project Task Gantt or in the standard Salesforce interface. You are informed if there's not enough information on the project tasks to generate records based on the attributes you select.

Generation Attributes

You can choose to generate task-driven resource requests or assignments based on a combination of:

Key: a = requires configuration.
Role [Any project task assignment fieldsª]
Resource [Any project task fieldsª]
External resource [Any user-defined fields on project tasksª]
Milestone [Any user-defined fields on project task assignmentsª]
Example
You might have project tasks for the Content Optimization milestone of a project, with project task assignments for the SEO Specialist role. You choose to generate resource requests based on Milestone and Role. For more examples, see " Bottom-Up Planning Examples".

Gaps Between Project Task Assignments

You can set how many days to allow between consecutive project task assignments before the process divides a single resource request or assignment, spanning the start and end dates of two or more project task assignments, into two. In this case, you can generate separate records for each time period based on your selected attributes. The value you enter is independent of the attributes selected to generate records, such as Role and Milestone. You can choose whether weekends are ignored or considered.

For more information, see "Setting Longest Gap Allowed".

Additional and User-Defined Fields

Your administrator can use a field set to add additional standard or user-defined fields to the list of generation attributes. These fields must be on the project task or project task assignment objects. For more information, see the "pta_fieldset_to_split _resource_request" setting.

Example
The user-defined field Work Breakdown Structure (WBS) Element is populated on your source project task assignments. You can choose to split task-driven resource requests by WBS element, creating a new resource request for every resource allocated to work on a specific WBS element.

Project-Level Summary

You can view the financial impact of task-driven resource requests and assignments on the project by viewing summary information on the project. For more information, see "Viewing Summary Information".

Notes
When assigning project tasks to external resourcesA person or entity that is external to your Salesforce organization. You can use external resources when assigning external staff, such as contractors, to project tasks., you should always select a role as well as an external resource. If the Resource Role field is empty when generating task-driven resource requests for external resources, you will be asked to either ignore or update the project task assignments.
If several project task assignments with the same resource or role exist on the project, they are combined to create a single resource request.

Related Tasks

Generating Assignments From Tasks

Generating Resource Requests from Tasks

Creating Resource Demands from Project Task Gantt

Viewing Summary Information

Creating Resource Requests

Adding a Task

Reference Materials

Generate Resource Requests from Project Tasks Fields

Unfilled Resource Requests Fields

Resource Request Fields

Project Task Fields

Project Task Assignment Fields

© 2009-2015 FinancialForce.com, inc All rights reserved. FinancialForce and FinancialForce.com are registered trademarks, and the FinancialForce.com logo is a trademark. Other product names appearing herein may be trademarks.
This document contains proprietary information of FinancialForce.com, inc and its licensors, and is subject to change without notice.