Generating Assignments From Tasks

  1. Click Generate Assignments on the Project Tasks related list of the project detail page that you are generating assignments for. Project tasks must have one or more project task assignments.
    Or, on Project Task Gantt, click Create Resource Demand and then Create Assignments.
  2. Select some attributes to base the generated assignments on. You can only select Milestone together with Role, Resource, or External Resource. Custom attributes may be available to select if configured by your administrator.
  3. Optionally, in the Longest Gap Allowed (Days) field, enter the duration of the longest gap, including weekends, permitted between consecutive project task assignments before a single assignment is divided into two. To ignore weekends when calculating gap duration, select Ignore Saturdays or Ignore Sundays.
    Tip
    If you don't enter a value, the process ignores gaps in the task schedule and generates an assignment that spans the start and end dates of the source project task assignments.
  4. Click Preview Assignments.
  5. Preview the assignments, including scheduled hours, cost rate, bill rate, duration, and the proposed resource to be assigned.
    Tip
    The proposed quantity and field values of the assignments depend on which attributes you select. Try a combination that reflects how much information is on your project task assignments.
  6. Deselect any previewed assignments that you want to discard.
  7. Click Generate to save the records to your organizationA deployment of the Salesforce/FinancialForce applications with a defined set of licensed users. Your organization includes all of your data and applications, and is separate from all other organizations. . The new task-generated assignments are displayed on the Unfilled Resource Requests page, along with summary information.
  8. Optionally, delete any assignments that you no longer want.
Notes
If several project task assignments exist on the project with the same resource or role, these are combined to create a single assignment.
Project task assignments for which a resource role cannot be derived are ignored when generating assignments from tasks.
You must have been granted the Staffing permission control in order to generate assignments from tasks.

Concept Information

Task-Driven Resource Requests and Assignments Overview

Bottom-Up Planning Examples

Bottom-Up Planning

Resource Requests

Project Task Gantt (Task Manager)

About Tasks

Reference Materials

Generate Resource Requests from Project Tasks Fields

Unfilled Resource Requests Fields

Resource Request Fields

Project Task Fields

Project Task Assignment Fields

© 2009-2015 FinancialForce.com, inc All rights reserved. FinancialForce and FinancialForce.com are registered trademarks, and the FinancialForce.com logo is a trademark. Other product names appearing herein may be trademarks.
This document contains proprietary information of FinancialForce.com, inc and its licensors, and is subject to change without notice.