In Project Task Gantt you can create a task dependency relationshipA relationship between two tasks. If a task is completed early or late, this has an effect on the start and end date of the task that succeeds it. between two tasks with one of these dependency types:
You can also specify a lagWhen a depenency relationship between project tasks exists, this term refers to the time gap added at the end of a task before the succeeding task can start. The default lag is 0. time on a task dependency relationship.