Editing a Task Dependency Relationship

There are several ways in which you can edit a task dependency relationship.

To edit a task dependency relationship in the Schedule pane:

  1. Double-click the arrow representing the relationship that you want to edit.
  2. If required, select the type of dependency that you want for the relationship. Choose one of the following from the Type drop-down list:
  3. If required, enter the lagWhen a depenency relationship between project tasks exists, this term refers to the time gap added at the end of a task before the succeeding task can start. The default lag is 0. time you want in the Lag field.
    Note
    When creating or editing a project task dependency in Project Task Gantt, enter the lag time you want in days. When creating or editing a project task dependency record in Salesforce, enter the lag time you want in multiples of 24 hours. For instance, if you want a lag time of two days and you are editing the project task dependency in Salesforce, enter 48 in the Lag Time (Hours) field. If you are editing the record in Project Task Gantt, enter 2 days in the Lag field.
  4. Click OK.

To edit a task dependency relationship using the Task Editor popup:

  1. In the Schedule pane, double-click the successor task of the dependency relationship that you want to change.
  2. Click the Predecessors tab.
  3. If required, edit the Task Name, Type and Lag fields of the dependency relationship that you want to change.
  4. Click OK.

Concept Information

Project Task Gantt (Task Manager)

About Tasks

About Task Dependency Relationships

Related Tasks

Managing Projects

Viewing Tasks

Viewing Task Details

Changing Start and End Dates

Adding a Task

Adding a Task Dependency Relationship

Deleting a Task Dependency Relationship

Assigning Resources or Roles to a Project Task

Closing Gantt Task Management

Deleting Tasks

Editing Project Task Details

Moving Tasks

Printing the Project Plan

Saving Changes

Searching

Undoing and Redoing Changes

Viewing the Critical Path

Zooming

Creating Resource Demands from Project Task Gantt

Associating Project Tasks with Milestones

Reference Materials

Project Task Gantt Fields

Project Task Gantt Settings and Preferences

© 2009-2015 FinancialForce.com, inc All rights reserved. FinancialForce and FinancialForce.com are registered trademarks, and the FinancialForce.com logo is a trademark. Other product names appearing herein may be trademarks.
This document contains proprietary information of FinancialForce.com, inc and its licensors, and is subject to change without notice.